Approved document S Infrastructure for the charging of electric vehicles
Approved Document S: infrastructure for charging electric vehicles, was published by the Department for Levelling Up, Housing and Communities on 15 December 2021. It provides technical guidance regarding the installation of charge points required by Part S of the Building Regulations.
Part S of the Building Regulations requires that certain buildings with associated parking must have access to electric vehicle charge points.
Very broadly, for new residential developments, a charge point is required for each parking space, with some exceptions. Where no associated parking spaces are provided, there is no requirement to instal a charge point.For non-residential developments with more than 10 parking spaces, one space must have access to a charge point, and cable routes must be provided to 20% of the other spaces. The charge points need to provide a minimum of 7kW to an untethered charger.
It sets an average cost cap of £3,600 for all work involved in installing a charge point. If the cost exceeds this, only the cable routes themselves need to be installed. Where the cost of is more than 7% of the total cost of a major renovation, there is no requirement to instal either electric vehicle charge points, or the cable routes if the cost of the cable routes is more than 7%.
Approved Document S applies to:
- New residential and non-residential buildings.
- Buildings undergoing a material change of use to dwellings.
- Residential and non-residential buildings undergoing major renovation.
- Mixed-use buildings that are either new, or undergoing major renovation.
Approved Document S came into effect on 15 June 2022, but does not apply to works where an initial notice was registered before 15 June 2022, provided the work starts before 15 June 2023.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.