Time at large
Construction contracts will usually include a date by which the works described in the contract should be completed. This is generally the date by which practical completion must be certified.
The phrase ‘time at large’ describes the situation where there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date.
Time can become at large because there is no clear completion date specified in the contract, or can be a situation that arises as a result of events (typically by agreement of the parties or by failure of the contract ‘machinery’), or if the contract does not allow the construction period to be extended.
It is not uncommon on construction projects that the works are not completed by the date for completion. If this is because of delays for which the contractor is responsible, then the contract will generally include a provision for them to pay liquidated damages to the client. These are pre-determined damages based on a calculation of the actual loss that the client is likely to incur if the contractor fails to meet the completion date. Some contracts require that a certificate of non-completion is issued as a pre-requisite to deducting liquidated damages.
If the works are delayed because of events for which the client is responsible (an act of prevention) or by agreed neutral events, the contracts will generally provide for an extension of time to be granted, changing the completion date (see relevant events). If contracts did not allow the construction period to be extended under such circumstances, then time would be at large. The client would then not be able to claim liquidated damages from the contractor as there would be no date against which they could be calculated and the contractor would then only have to complete the works in a 'reasonable' time. The client would only be entitled to damages if they could establish that the contract was not completed within a reasonable time.
It is important therefore that clauses describing relevant events cover all necessary eventualities, otherwise if an event occurs that is not covered, time will be at large.
NB: Construction contracts generally include a provision requiring that the contractor proceeds ‘regularly and diligently’ irrespective of whether it is apparent that the completion date will be achieved.
NB: NEC contracts refer to ‘compensation events’ rather than ‘relevant events’. Both parties must give early warning of anything that may delay the works, or increase costs. They should then hold an early warning meeting to discuss how to avoid or mitigate impacts on the project. In the case of a compensation event, if the contractor fails to give early warning of a possible delay to the works, or increase in costs, they will only be compensated for effects that would have remained even if they had given early warning.
[edit] Related articles on Designing Buildings Wiki
- Compensation event.
- Concurrent delay.
- Extension of time.
- Just-in-time manufacturing.
- Liquidated damages.
- Relevant event.
- Time of the essence.
[edit] External references
- Multiplex Construction v Honeywell Control Systems.
- Time at Large - an Explanation, Andy Hewitt.
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.






















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.