Self-build home: Submit a planning application
Introduction.
Depending on the procurement route that has been adopted, activities in this stage may be carried out by the self builder, their consultants, a design and build contractor or a kit house supplier.
Before construction can begin, it is necessary to obtain planning permission. Many clients will be unwilling to commit to paying fees for detailed design until they have received planning permission, and on particularly high-risk projects, the client may wish to obtain outline planning permission before they committ to any significant expenditure.
Procedure.
An application for planning permission may be a detailed planning application, or if there was already an outline planning permission for the site, may be a reserved matters application for the details of the design.
Before making a planning application it is important to contact the local planning authority:
- To find out when planning meetings are held and what procedures are followed.
- To agree the information that will be provided in the application and the fee payable.
- To gauge their likely reaction to the proposed development.
- To discuss planning conditions or planning obligations that may be imposed on the development (self-build homes are exempt from the Community Infrastructure Levy).
Records should be kept of all communications with the local planning authority.
For information about what might be required as part of a planning application see Detailed planning application. There may be additional requirements for developments in conservation areas, or works to listed buildings.
It is important that the self builder checks a draft planning application before it is submitted to ensure it properly reflects the agreed design and that the proposed project is affordable.
Once an application has been submitted, it may be necessary to respond to questions from the local planning authority and it can be beneficial to make representations to the planning committee. After consideration of comments received, or following the decision (which may include planning conditions or planning obligations), it may be appropriate to submit a revised application, or to lodge a planning appeal.
If the site does not have a postal address, an application to obtain one should be made once planning permission has been granted. Utilities companies will be reluctant to connect services without a formal postal address. See applying for new postal addresses for more information.
See also the government guide Better connected: a practical guide to utilities for home builders.
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..