Undervoltage
BSRIA Power quality guide (AG 2/2000) was written by C C Pearson and V Uthayanan and published by BSRIA in July 2000. It states:
Variations in supply voltage outside the normally accepted limits of ± 10% are subdivided according to the length of the variation.
Long duration variations encompass rms deviations at power frequencies for longer than one minute. EN 50160 specifies the steady state voltage tolerances expected on a power system. A voltage variation is considered to be of long duration when the limits are exceeded for more than 3 minutes (the international standards use a period of one minute).
Long duration variations can be:
- sustained interruptions
- undervoltages
- overvoltages.
An undervoltage is a decrease in the rms ac voltage to less than 90% at the power frequency for a duration longer than 3 minutes.
Undervoltages are the result of the events which are the reverse of the events that cause overvoltages. A load switching on or a capacitor bank switching off can cause an undervoltage until voltage regulation equipment on the system can bring the voltage back to within tolerances. Overloaded circuits can also result in undervoltages.
--BSRIA
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.