Maximum length of a flight of stairs
Approved Document K requires that dwellings with more than 36 risers in consecutive flights of stairs, have at least one change of direction, with a landing that has a minimum length equal to the width of the stairs.
For buildings other than dwellings, the maximum number of risers between landings is 16 for utility stairs, and 12 for general access stairs (or 16 in exceptional circumstances where the plan area is restricted). There should not be any single steps.
A utility stair is '...a stair used for escape, access for maintenance, or purposes other than as the usual route for moving between levels on a day-to-day basis.'
A general access is '...a stair intended for all users of a building on a day-to-day basis, as a normal route between levels.’
The requirements for the rise and going of stairs are set out below:
Min rise (mm) | Max rise (mm) | Min going (mm) | Max going (mm) | |
Private stair | 150 | 220 | 220 | 300 |
Utility stair | 150 | 190 | 250 | 400 |
General access stair | 150 | 170 | 250 | 400 |
This gives, for example, a maximum pitch for a private stair of 42 degrees.
The normal relationship between the rise and the going is that 2 x the rise + the going should be between 550mm and 700mm.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A call for prevention and sensitive re-use.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
BSA residential sector competence standards guidance
BSAS 01:2024 Organisational Capability Management System Standard - Competence Assurance.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.