How long does planning permission last
Before 1968, there was no limit on the duration of planning permissions. Between 1968 and 2009, the duration of a permission was generally set out in the conditions to the permission, often limited to 5 years within which time construction had to begin, although it was sometimes possible to extend this by applying to vary the condition.
However, since 2009, unless the permission states otherwise, development should begin within 3 years of the date permission was granted.
The development is considered to have begun ‘…on the earliest date that a "material operation" in connection with the development is started’, that is:
- Any work of construction in the course of the erection of a building.
- Any work of demolition of a building.
- The digging of a trench which is to contain the foundations, or part of the foundations, of a building.
- The laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned (above).
- Any operation in the course of laying out or constructing a road or part of a road.
- Any change in the use of any land which constitutes material development.
Ref Town and Country Planning Act 1990, Section 56.
Lawfully commencing the development works may first involve satisfying conditions applied to the permission.
If the development has not commenced within three years, the permission will be considered to have expired, and if the applicant still wished to proceed with the development, they will need to renew the application. Renewal is generally less onerous than making a fresh application, but a fee is payable. If however, the conditions under which the original permission was granted have changed, it may be necessary to make a fresh application.
Once the development has commenced, the permission remains in place unless the local authority serve a completion notice. If such a notice is served, the development must then be completed within 12 months.
If an outline planning application has been made, then the relevant reserved matters applications must be made within three years. The permission will then last for a further 2 years.
See also: How long does it take to get planning permission.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Community Infrastructure Levy.
- Design and access statements.
- Detailed planning application.
- Environmental impact assessment.
- Extensions to time limits for implementing existing planning permissions.
- How long does it take to get planning permission.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- The difference between planning permission building regulations approval.
Featured articles and news
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Comments