BIM Development for the Crossrail Farringdon Station
Bam Ferrovial Kier's (BFK) goal at Farringdon was to link programme, model and design information so that it could be accessed by stakeholders from a single source at any stage of the life cycle of the asset.
The joint ventyre selected BIMXtra software from Clearbox to achieve this goal, working with software developers to further adapt the BIMXtra platform for its complex requirements. Farringdon’s BIMXtra platform is now compatible with the majority of computer aided design (CAD) systems, enabling design schedules to be automatically populated with the geometric data from different CAD models.
BFK’s design team can also add non-geometric information directly onto the schedules during the design process. All information is automatically linked back to model components. One of BIMXtra’s major advantages is the streamlining of data gathering for asset management: Instead of being transposed by hand, a time consuming activity that is highly vulnerable to human error, data is generated through the linked design schedules. The delivery format can be set at any stage and the process is entirely automated. BFK predicts that the resulting CAD time savings for services subcontractors over the life cycle of the asset can be measured in man-years.
This project was the Merit Award Winner, Digital Innovation Award, in the CIOB International Innovation and Research Award 2014.
The Judge's said, “The applicants demonstrated an advanced implementation of BIM technologies on a complex infrastructure project. They not only showed the simultaneous interrogation of multiple models developed in different software packages, but also the collaborative working relationship which included the client and software consultant. The judging panel was impressed by their enthusiasm in applying a range of BIM technologies.”
--CIOB
Featured articles and news
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.