Sequential test
A flood risk assessment is required for most proposed developments that are within a designated flood zone.
A sequential test may be required as part of a flood risk assessment. It compares the site for a proposed development with other available sites to determine which has the lowest flood risk.
A sequential test is required if:
- The development is in flood zone 2 or 3, AND
- A sequential test has not already been done for a development of the type proposed on the proposed site.
A sequential test is not required if:
- The development is a ‘minor development’ OR
- The development involves a change of use, unless it is a caravan, camping chalet, mobile home or park home site OR
- It is a development in flood zone 1, unless there are flooding issues in the area of the development.
The sequential test must conclude whether any of the alternative sites that have been identified have a lower risk of flooding than the proposed site. It should be submitted along with the flood risk assessment and the planning application to the local planning authority.
If the sequential test shows that it is not possible to use an alternative site, it may be necessary to undertake an exception test. This shows how flood risk will be managed on the proposed site and demonstrates that the sustainability benefits of the development to the community outweigh the flood risk.
For more information see: https://www.gov.uk/guidance/flood-risk-assessment-the-sequential-test-for-applicants
[edit] Related articles on Designing Buildings Wiki
- BREEAM Flood risk management.
- BREEAM Surface water run-off.
- Design flood event.
- Design flood level.
- Flood and Water Management Act.
- Flood defences
- Flood plain
- Flood risk
- Flood risk assessment.
- Flood risk management plan
- Flood zone
- Flood.
- Minor development.
- Planning for floods.
- Property flood resilience
- Sustainable urban drainage systems.
Featured articles and news
50th Golden anniversary ECA Edmundson apprentice award
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Digital technology, transformation and cybersecurity
Supporting SMEs through Digitalisation in Construction.
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down one billion pounds
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.