Performance specified work in construction contracts
The phrase ‘performance specified work’ refers to aspects of a building development that are identified in contract documentation to be designed by contractors or suppliers.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further design by the contractor, to prescriptive (closed) specifications where the design is already complete when the project is tendered.
Most projects involve a combination of performance and prescriptive specifications. Items crucial to the design may be specified prescriptively (such as external cladding) whilst less critical items, or items requiring specialist design may be specified only by performance (such as service lifts).
Performance specifications describe the result that is required from particular items and leave it to the contractor or supplier to satisfy that requirement. In effect it requires them to complete the design. The nature of the performance required is typically defined by the desired outcome, or by reference to standards. See Performance specification for more information.
Performance specified work is increasingly common as buildings become more complex and the supply chain becomes more integrated, with contractors and suppliers having greater involvement in design at an earlier stage of the project.
Performance specified work used to be most commonly defined in a ‘contractors designed portion’ as a supplement to the main contract, but increasingly now it forms part of the requirements of the main contract itself.
Separate sub-contractor design agreements are available where the main contractor is to design specific parts of the works and a sub-contractor is to design part or all of sub-contract works.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.