Performance specified work in construction contracts
The phrase ‘performance specified work’ refers to aspects of a building development that are identified in contract documentation to be designed by contractors or suppliers.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further design by the contractor, to prescriptive (closed) specifications where the design is already complete when the project is tendered.
Most projects involve a combination of performance and prescriptive specifications. Items crucial to the design may be specified prescriptively (such as external cladding) whilst less critical items, or items requiring specialist design may be specified only by performance (such as service lifts).
Performance specifications describe the result that is required from particular items and leave it to the contractor or supplier to satisfy that requirement. In effect it requires them to complete the design. The nature of the performance required is typically defined by the desired outcome, or by reference to standards. See Performance specification for more information.
Performance specified work is increasingly common as buildings become more complex and the supply chain becomes more integrated, with contractors and suppliers having greater involvement in design at an earlier stage of the project.
Performance specified work used to be most commonly defined in a ‘contractors designed portion’ as a supplement to the main contract, but increasingly now it forms part of the requirements of the main contract itself.
Separate sub-contractor design agreements are available where the main contractor is to design specific parts of the works and a sub-contractor is to design part or all of sub-contract works.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.