Performance specified work in construction contracts
The phrase ‘performance specified work’ refers to aspects of a building development that are identified in contract documentation to be designed by contractors or suppliers.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further design by the contractor, to prescriptive (closed) specifications where the design is already complete when the project is tendered.
Most projects involve a combination of performance and prescriptive specifications. Items crucial to the design may be specified prescriptively (such as external cladding) whilst less critical items, or items requiring specialist design may be specified only by performance (such as service lifts).
Performance specifications describe the result that is required from particular items and leave it to the contractor or supplier to satisfy that requirement. In effect it requires them to complete the design. The nature of the performance required is typically defined by the desired outcome, or by reference to standards. See Performance specification for more information.
Performance specified work is increasingly common as buildings become more complex and the supply chain becomes more integrated, with contractors and suppliers having greater involvement in design at an earlier stage of the project.
Performance specified work used to be most commonly defined in a ‘contractors designed portion’ as a supplement to the main contract, but increasingly now it forms part of the requirements of the main contract itself.
Separate sub-contractor design agreements are available where the main contractor is to design specific parts of the works and a sub-contractor is to design part or all of sub-contract works.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.