U-values are used to measure how effective elements of a buildings fabric are as insulators. That is, how effective they are at preventing heat from transmitting between the inside and the outside of a building. The lower the U-value of an element of a building's fabric, the more slowly heat is able to transmit through it, and so the better it performs as an insulator.
U-values are measured in watts per square metre per degree Kelvin (W/m²K). So for example, if we consider a double glazed window with a U-value of 2.8, for every degree difference in temperature between the inside and outside of the window, 2.8 watts will be transmitted every square meter.
However, the situation for ground floors is more complicated than this.
The ground floor is not generally exposed to the weather, but faces, or sits above the ground. Unlike external conditions, the ground has a relatively constant temperature, typically 8 - 11° C in the UK. As a result, the thermal performance of the ground floor is dependent on the shape of its perimeter and the overall area it covers, as these determine the extent to which the floor is exposed to external conditions.
The smaller the floor and the greater the length of the perimeter exposed to the outside, the poorer its thermal performance and so the more insulation will be required to comply with the building regulations. So a domestic building may need to have the whole of the ground floor insulated, while a larger commercial building may only require insulation at the perimeter of the floor.
The PA ratio (perimeter area ratio, or P/A ratio) is a measure of the degree to which the perimeter of the floor is exposed:
PA = exposed perimeter (m) / floor area (m²).
The lower the PA ratio, the better the thermal performance of the floor.
The floor area is calculated from the internal surfaces of the external walls, and includes all heated spaces, but not unheated spaces that are outside of the insulated body of the building. Exposed perimeters include external perimeters and perimeters that connect to unheated spaces outside of the insulated body of the building.
The PA ratio, in combination with information about the construction of the floor (which will determine its U Value) can be used to calculate the amount and thickness of insulation required to comply with the building regulations.
Some insulation manufacturers provide tables or calculating tools that can be used to determine the amount of insulation required for a given floor type and PA ratio.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Cavity wall insulation.
- Conventions for calculating linear thermal transmittance and temperature factors.
- Computational fluid dynamics.
- Floor insulation.
- Heat transfer.
- Insulation specification.
- Limiting fabric parameters.
- R-value.
- Roof insulation.
- Solid wall insulation.
- Standard Assessment Procedure SAP.
- U value.
- U-value conventions in practice: Worked examples using BR 443.
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.