NEC Option A: Priced contract with activity schedule
Contents |
[edit] What is NEC?
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It is now in its fourth edition, NEC4.
The Engineering and Construction Contract (ECC) is the most frequently used, and can be adopted on projects such as infrastructure, buildings, highways and process plants. It is used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
[edit] What is option A?
Option A is a priced contract with an activity schedule, which relates to a programme where each activity is allocated a price and interim payments are made against the completion of those activities. The contractor largely bears the risk of carrying out the work at the agreed prices.
The advantage of using an activity schedule is that it simplifies the administration of the interim payment process.
[edit] How are payments calculated?
The activity schedule on these types of project is submitted together with a contract programme as part of the tender.
The activity schedule is a more important document under Option A than under Option C, as it has a significant effect on the contractor’s cash flow by directly effecting the timing and payment amount.
The sum that is due to the contractor in each assessment period is defined as the total of:
- Each group of completed activities (those without defects).
- Each completed activity not in a group.
Only when the whole of an activity is complete does the payment become due to the contractor. There is no provision for part payment.
[edit] Related articles on Designing Buildings
- Activity schedule.
- Conditions of contract.
- Construction contract.
- Contract documents.
- Contractor's working schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
- NEC3.
- Right to payment.
- Term contract.
Featured articles and news
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.






















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.