Mitigation in the construction industry
The term ‘mitigate’ means to make less severe or serious.
This can be important in the construction industry in a number of different circumstances.
- In relation to project delays, it refers to minimising the impact of the risk event (an event or cause of delay or disruption). For example, acceleration might be used to mitigate a delay. Where there is a claim for an extension of time, the contractor may be required to mitigate the delay and any resulting loss, even where the fault is not their own.
- In terms of losses incurred, it can refer to claimant's duty to mitigate their loss. A claimant will generally not be allowed to recover damage which could have been avoided had the claimant acted reasonably. For more information see: Mitigation of loss.
- In relation to planning policy, planning obligations or planning conditions might be used to mitigate or compensate for the negative impacts of a development. For more information see: Planning obligation and planning condition.
- In terms of risks, a contingency plan might be enacted to mitigate project risks, such as adverse weather, industrial disputes and so on. For more information see: Contingency plan.
Mitigation strategies might also be used in relation to:
- Environmental impact.
- Loss of habitat.
- Carbon emissions.
- Flood protection.
- Duty to warn.
A handbook on environmental impact assessment, 4th edition, published by Scottish Natural Heritage in 2013, suggests that:
These are the measures taken to avoid, cancel or reduce adverse impacts of a project. They are:
- Avoidance measures: Designed to avoid or eliminate any adverse impacts arising in the first place, including alternative or ‘do nothing’ options;
- Cancellation measures: Designed to nullify or cancel out any adverse effects of a project before adverse effects are felt;
- Reduction measures: Designed to minimise or at least reduce adverse impacts remaining after avoidance and cancellation measures have been applied to a project.
Culvert, screen and outfall manual, (CIRIA C786) published by CIRIA in 2019, suggests that the mitigation hierarchy is typically:
[edit] Related articles on Designing Buildings Wiki
- Consequential loss.
- Planning condition.
- Planning obligation.
- Contingency plan.
- Risk.
- Environmental impact assessment.
- Relevant event.
- Extension of time.
- Duty to warn in construction.
[edit] External references
- Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
Featured articles and news
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targetted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
ICE and BSI launch revised PAS 128 standard.
The revised standard for mapping underground utilities.
Launching the UK net zero carbon buildings standard.
Cross-industry steering group seeks support in delivery.
How to write an inspection and test plan.
Help us update process pieces from your field.
APM report explores existing practice.
Previous reflections on mental health with CIAT.
COVID-19 and the importance of mental wellbeing.
IHBC accreditation recognised by CSCS
As Professionally Qualified Person (PQP).
The Queens speech; bill by bill for 2022.
In order of relevance and with industry responses.
Mental Health awareness week, May 9-15.
Raising awareness of the impacts of loneliness.
Rapidly renewable materials and construction.
The list is growing, and in more ways than one.
Personal experiences of infrastructure maintenance issues.
We shouldn’t build new, If we can’t maintain what's built.
Mass timber: challenges and potential solutions.
Timber Accelerator Hub phase 1 report