How to appoint a contractor
Contents |
[edit] Introduction
Contractors are organisations appointed by clients (sometimes referred to as employers) to carry out construction works. This role is vital to the success of a project, and so great care should be taken to ensure an appropriate contractor is selected. This may involve seeking advice from consultants if the client is inexperienced.
In the construction industry, the process of selecting a contractor is generally referred to as ‘tendering’ and involves preparing tender documents that describe the project, and then inviting tender submissions from prospective contractors from which as selection can be made.
This article describes the process commonly followed for appointing the contractor after they have been selected. Other processes may be used on certain types of projects, such as Private Finance Initiative (PFI) projects.
- For information about how to put together a list of potential contractors see: How to find a contractor.
- For information about selecting a contractor from a list of potential contractors see: How to select a contractor.
[edit] Contract award
All tenderers should be informed of the decision to award the contract to a particular tenderer.
If OJEU procedures are being followed, it may be necessary to publish a formal contract award notice. A ‘standstill period’ may also be required. This is a pause of at least 10 calendar days between the decision being notified to all tenderers and the final contract conclusion. This allows for suppliers to challenge the decision.
[edit] Contract engrossment
Contract engrossment is the process of preparing the final agreed form of contract and its schedules and appendices so that it can be executed (signed).
Typically, the contract administrator (or sometimes the cost consultant) will collate the contract documents on behalf of the client and arrange for the printing and execution of two copies, one for the client and one for the contractor. Alternatively, the client might retain one executed contract, with certified copies being issued to the contractor, this can avoid potential errors in preparing two contracts for execution.
It is vital to ensure that the contract uses the correct legal names for the contracting parties. This is not always as straight-forward as it sounds, and errors can render contracts unenforceable.
See for example:
- Genesis Housing Association Limited v Liberty Syndicate Management Limited.
- Derek Hodd Limited v Climate Change Capital Limited.
- Westshield Civil Engineering Ltd and Westshield Ltd v Buckingham Group Contracting Ltd.
The contractor may also be required to provide a performance bond, warranties, evidence of insurance cover and so on.
Contract award and contract execution may not necessarily happen at the same time. In fact it is relatively common (although not advisable) for contracts to remain unsigned until well after work has begun.
Contracts may be executed under seal (signed by the parties, witnessed and most importantly made clear that they are executed as a deed) or under hand (a 'simple contract' that is just signed by the parties).
Simple contracts and contracts under seal have different limitation periods. An action founded on simple contract cannot be brought after six years from the date on which the cause of the action accrued. The limitation period for a contract under seal is 12 years. In addition, unlike a simple contract, a contract under seal does not have to be supported by valuable consideration (payment).
See Contracts under seal v under hand for more information.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Contract award.
- Contract documentation.
- Contract engrossment.
- Contract negotiation.
- Contracts under seal v under hand.
- How to find a contractor.
- How to select a contractor.
- Procurement route.
- Project plans for building design and construction.
- Tender documents.
- Tender process.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.