How to calculate head office overheads and profit
Contents |
[edit] Introduction
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK) describes three different ways for calculating head office overheads and profit:
[edit] Hudson formula
(Overheads & profit / 100) x (contract sum x period of delay / contract period)
Overheads & profit: head office overheads and profit percentage in tender.
[edit] Emden formula
(Overheads & profit / 100) x (contract sum x period of delay / contract period)
Overheads & profit: head office overheads and profit percentage (actual).
[edit] Eichleay formula
- Step 1: Establish the head office overhead costs attributable to the contract by dividing the final contract sum (excluding the claim for head office overhead) by the total revenue for the contract period, then multiply the result by the total head office overhead costs incurred during the actual period of performance of the contract.
- Step 2: Divide the resulting figure by the number of days of actual performance of the contract, to establish a daily rate.
- Step 3: Multiply the resulting figure by the number of days compensable delay.
Ref https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.