Health and safety plan
The requirement for a Health and Safety Plan for construction was established by the Construction (Design and Management) Regulations (or 'CDM Regulations') in 1994. The regulations came into force on 31 March 1995.
The regulations were introduced to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced.
The original regulations required that the Planning Supervisor ensure a Pre-Tender Health and Safety Plan was prepared for contractors setting out:
- A general description of the construction work.
- The programme.
- Risks to the health or safety of any person carrying out the construction work.
- Other information enabling the contractors to demonstrate the competence and adequacy of resources.
- Other information enabling the contractors to understand and perform their duties under the regulations.
The Principal Contractor then ensured that during the construction phase the Health and Safety Plan contained information about:
- Arrangements for the project to ensure the health and safety of all persons carrying out the construction work and all persons who may be affected by the work.
- Information about arrangements for the welfare of persons carrying out the construction work.
However, the CDM Regulations were substantially revised in 2007. Amongst many changes:
- The role of Planning Supervisor was replaced with a new, more hands-on CDM Co-ordinator.
- The Pre-Tender Health and Safety Plan was replaced with Pre-Construction Information, provided by the client and checked by the CDM Co-ordinator.
- The Health and Safety Plan was renamed the Construction Phase Plan (CPP), developed by the Principal Contractor.
NB: Rather confusingly, the Construction Phase Plan is still sometimes referred to as the Construction Phase Health and Safety Plan.
[edit] Related articles on Designing Buildings Wiki
- Automated external defibrillator AED.
- CDM.
- CDM Co-ordinator.
- Construction phase plan.
- Emergency plan.
- Health and safety file.
- Planning supervisor.
- Pre-construction information.
- Principal contractor.
- Safety.
- Safety audit.
[edit] External references
Six things to include in the health and safety plan for a construction site
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.

















Comments
Out of date information - CDM regulations updated in 2015