Extra over (EO)
‘Extra over’ (EO) is a term that is often used when taking off for a bill of quantities (BoQ). Taking off is the process of identifying elements of construction works that can be measured and priced.
When taking off for a BoQ, the term ‘extra over’ can be used to refer to items that to a certain extent have already been measured, but have not been priced at the full value of all their labour and materials. A common example of this is when measuring drain pipes, for which the estimator may determine a cost based on the full length of the pipe measured along its centre-line, and then assess an ‘extra over’ cost for the additional cost necessary to pay for fittings such as bends and junctions. So the cost of a section of pipe with a bend is the cost of the length of the pipe plus the extra over cost for the bend.
EO items should be listed directly beneath the main item over which they are measured, as this simplifies the the interpretation of the BoQ by suppliers. If the EO item cannot be listed immediately beneath, reference should be given in its description in the main item it relates to.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.

















Comments
good explanation