Discharge of planning conditions
Contents |
[edit] Introduction
Rather than refusing a planning application, a planning authority might grant permission, but with attached planning conditions. Some conditions may require approval by the planning authority before development commences (such as agreeing the colour of materials), others can be discharged during the course of development (for example limits to site operating hours).
Conditions imposed on a planning permissions are set out in the decision notice. The nature of conditions varies depending on the nature of the development and should be tailored to deal with specific issues rather than standardised or used to impose unnecessary controls. The National Planning Policy Framework states that planning conditions should only be imposed where they are ‘necessary, 'relevant to planning and to the development to be permitted, enforceable, precise and reasonable in all other respects’.
[edit] Methods for discharging a condition
The exact method for applying to discharge a planning condition depends on the local planning authority and therefore consultation with them is advisable. Typically, their website may include a discharge of conditions application form that can be downloaded and submitted or they may advise that application should be made through the planning portal website.
If early consultation takes place with the local planning authority before the application is submitted, or before the planning committee meeting, it may be possible to broadly agree the nature of conditions that the planning committee are likely to impose and the method of discharge.
[edit] Fees
It is necessary for an applicant to pay a fee to the local planning authority when they apply for:
- Written confirmation that conditions have been discharged.
- Written confirmation that one or more of the conditions has been completed.
More information on fees is available from the Planning Practice Guidance website. Typically, a fee of £116 (or £34 for householder planning permission) is payable per submission in England, to discharge the requirements of a planning condition.
[edit] Duration
For straightforward cases a response to an application to discharge planning conditions should be given within 21 days. This includes situations in which the condition requires third party consultation for discharge. Planning authorities must provide notice of their decision within 8 weeks from the date the request was submitted. If after 12 weeks, no decision has been received (and even if an extension of time is agreed for discharging the condition), the fee must be returned to the applicant.
[edit] Failure to comply
All conditions attached to a planning decision must be complied with, and failure to do so could lead to planning enforcement action being undertaken against the applicant or could lead to the invalidation of the planning permission.
Local planning authorities may undertake inspections to check planning conditions have been discharged and to ensure that development is in compliance with the permission that has been granted.
[edit] Deemed discharge
In April 2015, the deemed discharge of planning conditions was introduced into the Town and County Planning Act 1990 by the Infrastructure Act 2015. Details of the provisions are set out in the Town and Country Planning (Development Management Procedure) Order 2015.
This allows certain types of planning conditions in England to be discharged upon application if a local planning authority has not notified the developer of their decision within the prescribed time period. This is intended to improve the use of planning conditions and enable development to start more quickly after planning permission is granted.
See Deemed discharge of planning conditions for more information.
[edit] Find out more
Related articles on Designing Buildings Wiki.
- Consultation process.
- Deemed discharge of planning conditions.
- Detailed planning application.
- Outline planning application.
- National Planning Policy Framework.
- Planning permission.
- Planning appeal.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligation.
- Viability test.
External references
Featured articles and news
Government consultations for the summer of 2025
A year of Labour, past and present consultations on the environment, the built environment, training and tax.
CMA competitiveness probe of major housing developers
100 million affordable housing contributions committed with further consultation published.
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.