Design and build: outline work plan
This is an outline work plan for a private sector design and build project. For other procurement routes, including public sector projects (which may be design and build), click here.
Clicking on the stages will open a detailed schedule of the tasks necessary to complete that stage. Together these tasks represent a single, consolidated project plan from the first moment it becomes apparent a project might be required, right through to post occupancy evaluation.
Design and build
Stage 1: Business justification.
Stage 2: Feasibility studies.
Stage 3: Project brief.
Stage 4a: Concept design (design by consultant team).
or
Stage 4b: Concept design (design by contractor).
Stage 5a: Detailed design (design by consultant team).
or
Stage 5b: Detailed design (design by contractor).
Stage 6: Production information.
Stage 7: Mobilisation.
Stage 8: Construction.
Stage 9: Occupation and defects liability period.
Stage 10: Post occupancy evaluation.
Moveable stages:
- Appointing consultants.
- Planning permission (design by consultants).
- Tender.
- Planning permission (design by contractor).
Notes
- Design and build projects involve appointing a contractor to design the development and also to construct it. The contractor might be appointed early in the project to carry out all of the design work, or later in the project to complete a design which others have begun. This means that design tasks can be attributed either to a consultant team or the contractor depending on whether the contractor has been appointed or not. As a consequence, we include two versions of the concept design stage, detailed design stage and also the process for applying for planning permission. The tender stage is moveable depending on when the contractor is appointed.
Featured articles and news
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Comments