Construction management: planning permission
Planning permission is a vitally important part of almost all projects, often making the difference between whether the project proceeds to design or not. Many clients will be unwilling to commit to paying fees for detailed design until they have received planning permission, and on particularly high-risk projects, the client may even wish to obtain outline planning permission before committing to any significant expenditure. As a consequence planning permission can be applied for at different stages of the project's development.
In this project plan, we suggest the construction manager is appointed on completion of concept design. Earlier or later appointment will result in some of the activities below being re-allocated between the consultant team and the construction manager (for example the role of cost consultant).
Contents |
[edit] Assessing the type of application
The lead designer, architect and client consider whether to make an outline planning application or detailed planning application.
The lead consultant co-ordinates advice from the consultant team on the likely need for an environmental impact assessment and advises the client. It is important that this is considered at a very early stage in the project as preparing an environmental impact assessment can take a considerable time and may influence decisions such as site selection. The client may seek a screening decision and/or a scoping study from the local planning authority.
[edit] Undertaking a consultation process.
The lead designer consults with the local planning authority (and other appropriate statutory and non-statutory authorities) to determine the preferred form of the application, dates of planning committee meetings, committee procedures, possible planning conditions and possible planning obligations (section 106 agreement), as well as the application of the community infrastructure levy and the requirement to undertake an external consultation process.
The cost consultant (or construction manager if appointed) advises on the cost effects of statutory requirements and other requirements including possible planning conditions and planning obligations (section 106 agreement).
The client considers advice from the lead designer and cost consultant (or construction manager if appointed) and, if necessary, instructs amendments to the design.
The client and lead designer consider the extent and nature of the external consultation process that will be undertaken. The client begins an external consultation process with assistance from the consultant team.
The client considers the results of the consultation process and instructs further revisions to the design if required.
[edit] Preparing a planning application.
The lead designer co-ordinates the preparation of a draft planning application and issues it to the client for consideration. The cost consultant (or construction manager if appointed) advises the client about any abnormal costs arising from the draft planning application.
The client considers the draft planning application and, if necessary, instructs the lead consultant to arrange a value management exercise.
[edit] Submitting a planning application.
The client submits (or instructs the lead designer to submit) the planning application, including the planning fee.
The client (or lead designer) consults with the local planning authority on the progress of the application and likely planning conditions and planning obligations (section 106 agreement). If necessary, the client and lead designer respond to questions from the local planning authority and make representations to the planning committee.
On receipt of a decision (or recommendation in the planning officers' report) the client, lead designer and construction manager (if appointed) consider the planning conditions and planning obligations (section 106 agreement) that have been, or are likely to be, imposed and, if necessary, instructs the lead consultant to revise the application. If required, the client re-submits (or instructs the lead designer) to re-submit the outline or detailed planning application.
If necessary, on receipt of the decision the client lodges a planning appeal.
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.