Common refusals of extensions of time
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor should give written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.
Common reasons for the refusal of an application for extensions of time include:
- Where the contractor has underperformed, for example, as a result of insufficient workforce or failure to obtain plant, goods or service.
- When there has been poor, but not exceptionally adverse weather.
- When the evidence or other information presented to demonstrate that the contractor has suffered irrecoverable delays is insufficient.
- If an extension of time has already been given for that event.
- Where more than one event occurs at the same time. See Concurrent delay for more information.
- The event cited does not constitute a relevant event.
- An event does not constitute force majeure.
- An event does not constitute a specified peril.
- The contractor has not taken steps to mitigate the delay
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Change order.
- Compensation event.
- Contract administrator.
- Contract claims.
- Culpable delay.
- Delay damages.
- Extension of time.
- Extension of time - approval letter example.
- How to prepare a claim for an extension of time.
- Practical completion.
- Project programme.
- Time certainty.
- Time extension.
- Time Risk Allowance TRA.
- Variations.
Featured articles and news
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.