Self-build home: Appoint a contractor to construct the home
Preparing tender documents.
Before appointing a contractor to construct the home, it is important to decide:
- The form of contract and contract conditions.
- Requirements for contractual warranties and performance bonds.
- Works that will not be part of the contract.
- The dates for commencing and completing the works and any phasing requirements.
The designer should co-ordinate the preparation of tender documentation, a pre-tender estimate (the final estimate of the likely cost of the works) and a cash flow projection (so that the requirement for funds is known).
The tender documentation provides a detailed description of the works that is issued to prospective contractors (tenderers) so they can prepare an offer (tender) for carrying out the works.
The tender documents might include:
- A letter of invitation to tender.
- The form of the tender submission that is required from prospective contractors. The more prescriptive this is about what is required, the easier it will be to compare tenders from different prospective contractors.
- Preliminaries. A description of the project that allows the contractor to assess costs which, whilst they do not form a part of any package of works, are required by the method and circumstances of the works, such as; contractors site huts, site hoardings, scaffolding, site plant and so on.
- The form of contract and contract conditions.
- The tender pricing document. Effectively this is an unpriced bill of quantities onto which contractors enter the prices, rates and totals that constitute their offer. Requiring contractor's to present their offer in this way makes it easier to compare submissions by different contractors. It can also help negotiations, by allowing easy identification of areas where one contractor may be proposing to charge significantly more than another.
- Design drawings.
- Specifications.
Selecting a contractor.
Potential contractors might be identified by:
- Advertising.
- Research.
- Recommendation.
- Existing relationships.
Interviews might then be carried out to produce a short list that appear suitably experienced, available and easy to work with.
The designer collates the tender documents and arranges dispatch to and return from the tenderers. It may be appropriate to arrange mid-tender interviews for the tenderers to answer questions, talk through alternative proposals, and to arrange site visits.
The designer co-ordinates assessment of the tenders received from contractors and may conduct further interviews. The designer prepares a tender appraisal report and negotiations are entered into with the preferred tenderer. A reserve tenderer may be selected in the event that negotiations are unsuccessful.
Before a decision is made to appoint the preferred tenderer, it is important to ensure adequate funding is in place.
The designer collates the contract documents and arranges for the execution of two copies, one for the self builder and one for the contractor. The contractor may be required to provide evidence of their insurance cover.
NB Self-build clients are ‘domestic clients’ for the purposes of the Construction (Design and Management) Regulations (health and safety regulations generally referred to as the 'CDM Regulations'), and so the client's duties under the regulations will generally fall to the contractor. See CDM for self-builders and domestic clients for more information.
Featured articles and news
Government consultations for the summer of 2025
A year of Labour, past and present consultations on the environment, the built environment, training and tax.
CMA competitiveness probe of major housing developers
100 million affordable housing contributions committed with further consultation published.
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.