Section 278 agreement - works to existing highways
Section 278 of the Highways Act 1980 allows a developer to carry out works to the public highway. This is generally necessary where planning permission has been granted for a development that requires improvements to, or changes to, public highways.
The agreement between the highway authority and the developer is called a Section 278 Agreement, and it may allow for items such as:
- Roundabouts.
- Priority junctions.
- Junctions with traffic lights.
- Right turn lanes.
- Improved facilities for pedestrians and cyclists.
- Improvements to existing junctions.
- Traffic calming measures.
The highway authority will be either Highways England for the strategic road network in England, or the local highway authority.
The agreement may include:
- Details of the relevant planning permission.
- The agreed design.
- Details of any bond required.
- Details of who will design and manage the works.
- The programme for the works.
- Provision for inspection and certification of the works.
- Costs.
The developer may be responsible for designing, carrying out and paying for the works to the satisfaction of the local highway authority, or the highway authority may carry out the works. The developer may also pay for all or part of works carried out by the highway authority if they are carried out in a way, at a time, or are modified to suit the developer.
In addition to the works themselves, the developer may be required to pay costs associated with:
- Making the agreement.
- Agreeing the scheme for the works.
- Permissions associated with the works.
- Land acquisition associated with the works.
- Administrative expenses incurred by the highway authority.
- Maintenance of the works (commuted sums).
If the developer is carrying out the works, there may be a requirement for a bond to cover the highway authority against the possibility that the developer fails to properly complete the works, for example if they become insolvent. The bond will be released incrementally until a twelve month maintenance period has elapsed after the works are complete.
The planning application associated with the development will generally establish the principles of the works required. The highway authority cannot then refuse to enter into an agreement for the developer to undertake the approved works as long as the works meet the appropriate standards.
If the developer fails to make agreed payments, or if the works are not carried out in accordance with the agreement, the highway authority is empowered to close the access to the site.
The procedure necessary to reach agreement can be time consuming and protracted, and so it is desirable to enter into discussion with the highway authority as early in the project as possible.
Section 278 Agreements are often entered into alongside Section 38 Agreements, which enable developers to ask the highway authority to ‘adopt’ new roads along with associated infrastructure such as drains, lighting and supporting structures. See Section 38 Agreement for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Highways.
- Manual of Contract Documents for Highway Works.
- Planning condition.
- Planning obligation (Section 106 Agreement).
- Planning permission.
- Reserved matters.
- Section 38 Agreement.
- Section 50 agreement.
- Section 184 agreement.
- Section 215.
[edit] External references.
Featured articles and news
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
Comments