Schedule performance index (SPI)
The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule.
As a ratio it is calculated by dividing the budgeted cost of work performed, or earned value, by the planned value.
For example:
- A project has a budgeted cost of £120,000.
- According to the schedule, 15% of the project should have been completed after one month (planned value). That is £120,000 x 15 / 100 = £18,000.
- But after a month, only 12% of the project has actually been completed (earned value). That is £120,000 x 12 / 100 = £14,400.
SPI = EV / PV = 14,400 / 18,000 = 0.8
This means that for every estimated hour of work, the project team is only completing 0.8 hours (just over 45 minutes).
If the ratio has a value higher than 1 this indicates the project is progressing well against the schedule. If the SPI is 1, then the project is progressing exactly as planned. If the SPI is less than 1 then the project is running behind schedule.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Cost performance index (CPI).
- Benchmarking.
- Design programme.
- Earned value.
- Fast-track construction.
- Key performance indicators KPI.
- Lead time.
- Programme for building design and construction.
- Project crashing.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External references
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
Its just 12/15 no need to multiply the percentage by the budget.
Indeed.