Schedule performance index (SPI)
The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule.
As a ratio it is calculated by dividing the budgeted cost of work performed, or earned value, by the planned value.
For example:
- A project has a budgeted cost of £120,000.
- According to the schedule, 15% of the project should have been completed after one month (planned value). That is £120,000 x 15 / 100 = £18,000.
- But after a month, only 12% of the project has actually been completed (earned value). That is £120,000 x 12 / 100 = £14,400.
SPI = EV / PV = 14,400 / 18,000 = 0.8
This means that for every estimated hour of work, the project team is only completing 0.8 hours (just over 45 minutes).
If the ratio has a value higher than 1 this indicates the project is progressing well against the schedule. If the SPI is 1, then the project is progressing exactly as planned. If the SPI is less than 1 then the project is running behind schedule.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Cost performance index (CPI).
- Benchmarking.
- Design programme.
- Earned value.
- Fast-track construction.
- Key performance indicators KPI.
- Lead time.
- Programme for building design and construction.
- Project crashing.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External references
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.
Comments
Its just 12/15 no need to multiply the percentage by the budget.
Indeed.