Reserved matters in planning permissions
Outline planning applications can be used to find out whether a proposed development is likely to be approved by the planning authority, before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage.
Reserved matters, also refers certain matters concerning the governance of the UK, where decisions may be taken by the UK Parliament at Westminster even though they have an effect in Scotland, Wales, Northern Ireland or the regions of England. Such reserved matters may also give allowance for devolved governments to implement slightly different regimes, though more directly, where matters are accepted areas where decision-making has been delegated by Parliament to the devolved institutions such as the Scottish Parliament, the Assemblies of Wales, Northern Ireland and London or to Local Authorities, these are referred to as devolved matters.
In terms of reserved matters and outline planning applications on the 10 August 2006, changes to the outline planning permission process came into force intended to make outline planning applications more 'detailed' and so to restrict the extent of reserved matters. Reserved matters that might be the subject of further applications once outline planning consent has been obtained can now include:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed in any way.
Outline permission is not a permission to start work on site. The permission notice will state which matters have been reserved for later approval. When all of the reserved matters have been approved, work may begin on the site.
Reserved matters applications should be submitted within 3 years of outline permission being granted.
Outline planning permission lasts for two years from the date reserved matters were approved, or three years from the date of the outline planning permission, whichever is the later.
[edit] Related articles on Designing Buildings
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments
If a reserved matters application in respect of a new road junction from a possible new housing development onto the main highway is unsupported by Highways England, on the grounds of unachievable visibility splay distances, must the Local Authority then turn down that application? What then happens to the original planning application for that access road, which was previously approved?