Midland Expressway Ltd v Carillion Construction Ltd & Others
The case of Midland Expressway Ltd. v Carillion Construction Ltd., Alfred MacAlpine Construction Ltd., Balfour Beatty Group Ltd., AMEC Capital Projects Ltd., John E. Price (No.2) [2005] concerned the new M6 toll road construction near Birmingham and is important with regard to Private Finance Initiatives (PFIs) and Public Private Partnerships (PPPs).
The four defendant contractors worked together as a joint venture called CAMBBA. A concession agreement was granted in 1992 by the Secretary of State to Midland Expressway Ltd. (MEL) for them to design, construct and operate the M6 Toll Road. MEL and CAMBBA entered into a design and construct sub-contract in 2000.
‘Equivalent project relief’ provisions were contained within the sub-contract which limited the sub-contractor’s (CAMBBA) right to payment for variations and delay to the amount that MEL was able to recover from the Secretary of State. A mechanism that was intended to ensure this in the sub-contract restricted the subcontractor’s right to adjudicate an issue until a relevant adjudication had been brought between MEL and the Secretary of State.
As a result of variations, CAMBBA made claims for additional payment which, when they were disputed, CAMBBA wished to refer to adjudication. In response, MEL applied for a declaration and injunction preventing them from referring the claim to adjudication, arguing that the sub-contract did not provide them with any jurisdiction. The correct dispute, according to MEL, was between the Secretary of State and CAMBBA, as they were only a conduit between them.
CAMBBA argued that the ‘equivalent project relief’ and adjudication provisions in the subcontract cut across the statutory entitlement under the Housing Grants, Construction and Regeneration Act (HGCRA). Section 108 states that a subcontractor is entitled to commence an adjudication ‘at any time’. As the design and construct contract was a legitimate ‘contract’ under HGCRA, the dispute could be referred to adjudication.
The Technology and Construction Court (TCC) agreed with CAMBBA, and it was held that the adjudication provisions in the sub-contract were invalid. The ‘pay when paid’ aspect of the ‘equivalent project relief’ provisions was viewed as infringing section 113 of HGCRA which sought to guard against such clauses. Therefore, CAMBBA did not have to wait to be able to refer the dispute to adjudication.
Since previously, ‘equivalent project relief’ provisions had ensured that contractors were able to act as conduits for subcontractor claims without having liability, the repercussions of the case were that limiting the right to adjudication could no longer be used as a mechanism for meeting that objective.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Civil engineers and environmental methods of construction
Can the profession use its skills to save the world from climate change?
How faulty science resulted in sanitation reform.
Conserving the Hilda Besse Building
Improving facilities, accessibility and overall appearance.
BSRIA IAQ topic guide published
Free download of TG 12/2021 available.
Electrotechincal mentors wanted
TESP works with The Youth Group to form skill sharing network.
OpenBuilt supply chain technology in development
Big tech collaborates on platform for the built environment.
Concerns raised over Future Buildings Standard
Letter signed by 21 organisations sent to MHCLG.
The infrastructure planning process
A look at the Government's strategic approach.
Steps to help reduce the spread of infection inside buildings.
Urban exploration and construction
This social media-centred hobby can be both dangerous and illegal.
Millwork wall treatment with a long and illustrious history.
Weekly workplace noise estimator tool
HSE introduces cumulative exposure calculator.
The Edwardians and their houses.
Cut off from civilian life for over 900 years.
Receive the Designing Buildings newsletter
Click the button to subscribe.