Freezing method for stabilising soils
Freezing can be used as a method of stabilising water-saturated soils and preventing collapse next to excavations. By freezing the soil until it becomes impervious, it enables workers and plant to operate safely inside the ‘ice wall’ that is formed. In this way, deep earthworks can take place.
In order to produce the low temperatures, steel freeze pipes are installed at approximately 1 m centres around the site that is to be excavated. The pipes are comprised of two tubes. The outer tube is 100-150 mm in diameter, is sealed at the bottom and connected at the top to a return pipe. The inner tube is 38-75 mm in diameter, is open at the bottom and connected to the flow pipe at the top.
These pipes carry chilled brine which is pumped down the inner tube. A refrigeration plant is used to cool the liquid, constantly re-circulating it through the pipes. The brine temperature ranges from -15 to -25-degrees, although the freezing medium must have a freezing point that is well below this temperature range, meaning that a solution of calcium chloride or magnesium chloride is often used.
For the method to be employed there must be moisture content of 8% of the voids. Using a brine medium, the time to obtain a wall of ice depends on the spacing of the pipes, the refrigeration quantity and the type of soil. For example, with pipes spaced at 1 m centres, a frozen wall measuring 1 m thick in sand and gravel takes 10-12 days, and 15-17 days in clay. An observation borehole in the centre of the treated area is sunk to determine whether the frozen wall is completely continuous and excavation work can begin.
Where rapid freezing is required, liquid nitrogen is used as the freezing medium, and this can reduce the freezing time to a few days.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.