Freezing method for stabilising soils
Freezing can be used as a method of stabilising water-saturated soils and preventing collapse next to excavations. By freezing the soil until it becomes impervious, it enables workers and plant to operate safely inside the ‘ice wall’ that is formed. In this way, deep earthworks can take place.
In order to produce the low temperatures, steel freeze pipes are installed at approximately 1 m centres around the site that is to be excavated. The pipes are comprised of two tubes. The outer tube is 100-150 mm in diameter, is sealed at the bottom and connected at the top to a return pipe. The inner tube is 38-75 mm in diameter, is open at the bottom and connected to the flow pipe at the top.
These pipes carry chilled brine which is pumped down the inner tube. A refrigeration plant is used to cool the liquid, constantly re-circulating it through the pipes. The brine temperature ranges from -15 to -25-degrees, although the freezing medium must have a freezing point that is well below this temperature range, meaning that a solution of calcium chloride or magnesium chloride is often used.
For the method to be employed there must be moisture content of 8% of the voids. Using a brine medium, the time to obtain a wall of ice depends on the spacing of the pipes, the refrigeration quantity and the type of soil. For example, with pipes spaced at 1 m centres, a frozen wall measuring 1 m thick in sand and gravel takes 10-12 days, and 15-17 days in clay. An observation borehole in the centre of the treated area is sunk to determine whether the frozen wall is completely continuous and excavation work can begin.
Where rapid freezing is required, liquid nitrogen is used as the freezing medium, and this can reduce the freezing time to a few days.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.