Discount rate in the construction industry
[edit] What is the discount rate?
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
NRM3: Order of cost estimating and cost planning for building maintenance works, defines a ‘discount rate’ as:
|
The percentage rate required to calculate the present value of a future cash flow (i.e. used for bringing future costs to a comparable time base). For example, if investing at 3 per cent interest, then the present value is discounted by 3 per cent as it is worth less than future earnings due to interest. The discount rate is a factor or rate reflecting the time value of money that is used to convert cash flows occurring at different times to a common time base. |
Where the present value is:
'...the cost or benefit in the future discounted back to some base date, usually the present day, at a given compound interest rate'.
NRM3 defines the ‘treasury discount rate’ as:
'…the rate specified as the discount rate by the UK Government Treasury to be used as the discount rate for public sector whole life costing calculations.'
[edit] Other definitions
Guide to developing the project business case, Better business cases: for better outcomes, published by HM Treasury in 2018, defines the discount rate as: ‘The annual percentage rate at which the present value of a £, or other unit of account, is reduced over time. This is applied to values that are at constant prices and has nothing to do with currency inflation.'
Life Cycle Costing (BG 67/2016), written by David Churcher and Peter Tse and published by BSRIA in March 2016, defines the discount rate as: ‘The percentage by which costs or benefits occurring one year in the future are deemed to be less valuable than costs or benefits today. In life cycle costing, the discount rate is the difference between the cost of capital and the inflation rate. For public sector projects, the discount rate is 3.5% per annum. Discount rates can be expressed using different time periods (such as months) provided the study period is expressed in a consistent manner.’
ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines discount rate as a: ‘Factor or rate reflecting the time value of money that is used to convert cash flows occurring at different times (ISO 15686-5).’
[edit] Related articles on Designing Buildings
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.