Design and build: outline work plan
This is an outline work plan for a private sector design and build project. For other procurement routes, including public sector projects (which may be design and build), click here.
Clicking on the stages will open a detailed schedule of the tasks necessary to complete that stage. Together these tasks represent a single, consolidated project plan from the first moment it becomes apparent a project might be required, right through to post occupancy evaluation.
Design and build
Stage 1: Business justification.
Stage 2: Feasibility studies.
Stage 3: Project brief.
Stage 4a: Concept design (design by consultant team).
or
Stage 4b: Concept design (design by contractor).
Stage 5a: Detailed design (design by consultant team).
or
Stage 5b: Detailed design (design by contractor).
Stage 6: Production information.
Stage 7: Mobilisation.
Stage 8: Construction.
Stage 9: Occupation and defects liability period.
Stage 10: Post occupancy evaluation.
Moveable stages:
- Appointing consultants.
- Planning permission (design by consultants).
- Tender.
- Planning permission (design by contractor).
Notes
- Design and build projects involve appointing a contractor to design the development and also to construct it. The contractor might be appointed early in the project to carry out all of the design work, or later in the project to complete a design which others have begun. This means that design tasks can be attributed either to a consultant team or the contractor depending on whether the contractor has been appointed or not. As a consequence, we include two versions of the concept design stage, detailed design stage and also the process for applying for planning permission. The tender stage is moveable depending on when the contractor is appointed.
Featured articles and news
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Comments