Consultant team start-up meeting
A consultant team start-up meeting should be held when members of the consultant team are appointed, before they begin work. It should be chaired by the client and attended by the consultant team. It is possible that consultants will not all be appointed at the same time, so it may be necessary to hold more than one start-up meeting.
The start-up meeting is an opportunity to:
- Introduce the parties to be involved, explain responsibilities and exchange contact details.
- Describe the organisational structure that will be adopted.
- Issue and discuss site information.
- Issue and discuss the preliminary business case (if appropriate).
- Issue and discuss the strategic brief.
- Issue and discuss the project execution plan.
- Agree working methods such as; methods of communication, means for reporting, approvals and decision making processes (consultants can sometimes programme client decisions into their work without first establishing that the programme suits the client), drawing protocols and standards, collaborative practices, document control strategies and so on.
- Discuss procurement options and tendering restrictions (such as OJEU procurement rules).
- Discuss CDM and other legislative obligations.
- Identify any additional members of the consultant team, specialist designers, specialist contractors or independent client advisers who should be appointed.
- Discuss the programme.
- Identify immediate tasks to be undertaken.
- Agree meeting schedules.
- Discuss the application of VAT.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.