Appointment of an adjudicator under JCT 98
This article needs more work. To help develop this article, click 'Edit this article'.
See also: Adjudication.
The process of appointment of an adjudicator under JCT 98 provisions:
- Clause 41A.1: either party may refer any dispute to adjudication
- Clause 41A.2: the adjudicator shall either be an individual agreed by both parties, or an individual to be nominated by the person named in the Appendix, provided that:
- Clause 41A.2.1: no adjudicator shall be agreed or nominated who will not execute the JCT standard agreement for appointment on an adjudicator, and
- Clause 41A.2.2: where either party has given notice of his intention to refer a dispute to adjudication then:
- any agreement by the parties must be reached with the object of securing the appointment of the adjudicator within 7 days of the notice
- any application to the nominator must be made with the object of securing the appointment of the adjudicator within 7 days of the notice
- once agreed or nominated, the parties shall execute with the adjudicator the JCT adjudication agreement
The particulars to be provided with the referral documents should include:
- Particulars of the dispute
- A summary of the contentions on which the referring party relies
- A statement of the relief or remedy that is sought
- Any material the referring party wishes the adjudicator to consider
- Referral documents should be copied to the other party
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.