Modular vs traditional construction
This article provides an outline of the important differences between modular and traditional construction methods:
- The term ‘traditional’ is often used to describe the types of linear construction, where each individual step is not only constructed entirely (or largely) on site, but also needs to be completed before the project can move on to the next phase.
- Modular construction is an off-site based construction method, during which individual components are manufactured (or ‘prefabricated’) in a factory, transported to the site entirely (or mostly) complete and assembled on location.
Both construction methods start in the same way – planning, design, approvals, site preparation and development. From that point forward, however, the differences begin:
Image source: Modscape
Pros and Cons of Modular Construction
Pros:
- Thanks to the ability for the project to run simultaneously on-site and in-factory, modular construction can be up to 50% quicker than traditional construction.
- As major parts of construction are handled within a factory, weather conditions are often irrelevant during the majority of the project.
- The factory-based manufacturing process allows not only for greater quality control during the manufacturing process but for many health and safety risks to be considerably reduced, if not eliminated,
- The process aims to minimise waste and reduce the project’s carbon footprint, as fewer people are travelling to the site and modules are produced directly to spec using Computer Aided Manufacturing.
- The impact on the community surrounding the construction site can be significantly reduced, due to much lower levels of noise and traffic during the project period
- The methods employed in modular construction can often benefit the energy efficiency and airtightness of the final construction
Cons:
- Access to the site must be considered from the very beginning, as it will need to allow for the delivery of large modules.
- Traditional construction allows for later design changes, while modular construction is unlikely to be able to factor these in, so early complete design sign off is crucial with clients.
- The logistics and planning of individual module assembly will need rigorous planning to ensure a smooth project.
Ultimately, each project should be considered individually. The method that is selected should match the ultimate desired outcome and the individual limitations of each project.
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Comments