Time extensions in construction contracts
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. In the United States, this is described as a time extension. The UK equivalent is an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit a time extension, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay. Time extensions are granted based on the contractor being able to demonstrate that the delay was caused by events beyond their control. The contract guidelines typically specify the provision of time extension requests.
There are various circumstances in which time extension requests will be valid, including:
- Delays are caused by the owner changing the design.
- A delayed start to the works by request of the owner.
- Site conditions (e.g. sub-surface conditions) that differ from the project plans.
- Exceptionally adverse weather.
- Variations to the original scope or contract required by the owner.
- Force majeure.
- Legal issues that affect project completion or the contractor’s performance.
- The supply of materials and goods by the owner.
There are various circumstances in which time extension requests will be deemed invalid, including:
- Delays are caused by subcontractors.
- When the workforce is insufficient.
- The contractor underperforms, i.e. by procuring long-lead items.
- Delays caused by normal adverse weather conditions.
- Where there is inadequate evidence that irrecoverable delays have not been caused by the contractor.
In order for a time extension to be granted it is important that the contractor is transparent and communicative in their dealings with the owner and the project team. The project manager must be informed at the earliest opportunity and, if they deem it valid, they will submit a formal time extension request. For further information, see What should be included in a time extension request?
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.