Third party opinion and fixed-fee mediation procedures
Contents |
[edit] Introduction
Construction contracts usually provide for disputes to be dealt with by agreed dispute resolution procedures involving mediation, adjudication and arbitration. Often a combination of all three.
On 6 November 2014, The RIBA launched two new dispute resolution schemes intended as alternatives to more formal processes:
- Third party opinion.
- Fixed-fee mediation.
These are fast, low-cost schemes intended for the resolution of low-level disputes that might otherwise cause delays to projects.
[edit] Third party opinion
The third party opinion procedure is intended for the resolution of technical issues or issues such as valuation. It involves the selection of an independent professional to give an opinion on the dispute and to make a recommendation for settlement. It is appropriate where the parties genuinely wish to settle the dispute and is entered into by consent, it is not part of the contract terms.
Submissions are limited to the two sides of A4 form each party with a maximum of 10 sides of supporting documents. A 5 hour time limit is applied. If a settlement is reached, the parties sign a binding agreement. The procedure may be abandoned at any time.
[edit] Fixed-fee mediation
The fixed-fee mediation procedure is intended for low-value disputes (up to £15,000) that the parties have a genuine wish to settle, and which can be resolved quickly. Mediators are selected from a list maintained by the RIBA to assist negotiations between the parties. If a settlement cannot be reached by negotiation, the mediator may suggest a settlement, but this is only binding if the parties wish it to be. If a settlement is reached, the parties sign a binding agreement. Mediation may be abandoned at any time.
The parties each set out the nature of the dispute on a single side of a A4. Mediation is conducted by telephone for no more than an hour. There can be one or two hours of preparation depending on the amount in dispute.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Alternative dispute resolution legislation.
- Arbitration.
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Contract claims.
- Dispute resolution boards.
- Expert witness.
- Housing Grants, Construction and Regeneration Act.
- Litigation.
- Mediation.
- Med-adjudication.
- Med-arbitration.
- RIBA.
- Scheme for Construction Contracts.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
















