Working up construction works
Contents |
[edit] Introduction
Working up (or creating a workup) refers to the process of collating the details of the measured elements of construction works before prices have been determined. This information is then used to produce an unpriced bill of quantities (BoQ).
An unpriced bill of quantities (BoQ) is essentially an estimate in the form of a template. It breaks down the work required on a project into tasks but has no measured quantity (or price) by each task. For more information see: Unpriced bill of quantities.
[edit] Taking off
Before working up takes place, elements are identified through the taking off process. The term taking off refers to the process of identifying elements of construction works that can be measured and priced. This is necessary to produce bills of quantities and requires that the design is complete and a specification has been prepared.
Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works.
For more information see: Taking off.
[edit] Workup sheets
The process of taking off includes calculating measurements of the components by number, length, area, volume, weight or time. All items must be accounted for through the take off process. This information is then entered on workup sheets.
Quantities from workup sheets are generally grouped based on work category. This information is then transferred to a summary sheet for pricing.
[edit] Workup and property purchasing
In the United States, the term workup can also be used to describe an estimate created for a prospective purchaser of a building lot, including the plan and options. In this instance, the workup takes place before the purchase agreement is signed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.