Schedule variance
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that schedule variance (SV) is: ‘…the cost comparison of what has been earned with what was budgeted. It measures the difference in value between the work planned and the work actually accomplished’
Schedule Variance (SV) = Budgeted Cost of Work Performed (BCWP) – Budgeted Cost of Work Scheduled (BCWS)
Or:
SV% = (SV/BCWS) x 100
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.
Bringing together expertise and creating cultural benefits.
CIOB celebrates positive Ofsted report.
The Building Safety Regulator announces a call for evidence.