Schedule variance
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that schedule variance (SV) is: ‘…the cost comparison of what has been earned with what was budgeted. It measures the difference in value between the work planned and the work actually accomplished’
Schedule Variance (SV) = Budgeted Cost of Work Performed (BCWP) – Budgeted Cost of Work Scheduled (BCWS)
Or:
SV% = (SV/BCWS) x 100
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.