Schedule variance
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that schedule variance (SV) is: ‘…the cost comparison of what has been earned with what was budgeted. It measures the difference in value between the work planned and the work actually accomplished’
Schedule Variance (SV) = Budgeted Cost of Work Performed (BCWP) – Budgeted Cost of Work Scheduled (BCWS)
Or:
SV% = (SV/BCWS) x 100
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Rising concern over construction worker wellbeing
Urgent need for open communication to address mental health issues.
New engineering alliance forms
Guidance offered on COVID-19 green recovery, building safety and more.
Providing strength and support above the joists.
Construction Products Regulator
Enforcer will test and investigate product safety.
London landmark receives a high tech upgrade
Underfloor air conditioning comes to 24 St James's Square.
Consultation on public right to buy unused public property.
Guidance for listed building alterations
IHBC resource offers improved consistency.
New laws to ‘retain and explain’ historic statues.
The principles and art of the possible. Book review.
From horse and cart to hypermarket.
Interdependent and interconnected
How elements and processes work together in a systems approach.
Quality Management in Construction
CIOB offers digital guide to proactive methods of working.