Schedule variance

Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that schedule variance (SV) is: ‘…the cost comparison of what has been earned with what was budgeted. It measures the difference in value between the work planned and the work actually accomplished’

Schedule Variance (SV) = Budgeted Cost of Work Performed (BCWP) – Budgeted Cost of Work Scheduled (BCWS)

Or:

SV% = (SV/BCWS) x 100