Cost performance index (CPI)
The cost performance index (CPI) is a measure of the financial effectiveness and efficiency of a project. It represents the amount of completed work for every unit of cost spent.
As a ratio, it is calculated by dividing the budgeted cost of work completed or earned value, by the actual cost of the work performed.
For example, if a project has a earned value (EV) of £20,000 but actual costs (AC) were £12,000:
CPI = EV / AC = 20,000 / 12,000 = 1.66
If the ratio has a value higher than 1 then it indicates the project is performing well against the budget. A CPI of 1 means that the project is performing on budget. A CPI of less than 1 means that the project is over budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.


















Comments
Bravo, que palabras..., el pensamiento magnfico volveremos al tema https://mixfilesmaker.com/