Retention of title in construction
Typically on construction projects, goods, materials or plant are not paid for until after they have been delivered to site. Even then, the contractual chain may mean that the client pays the main contractor at agreed intervals, and then the main contractor pays sub-contractors and so on.
This can put the supplier at risk, if the buyer (typically the contractor) defaults or becomes insolvent before payment is received. If the contractor has delivered the items and the client has received them in good faith then ownership may be disputed even if the supplier has not been paid in full.
A ‘retention of title’ clause (‘RoT, ‘Romalpa clause’ or ‘reservation of title clause’) allows a supplier to retain ownership of until specified conditions have been met, for example, until payment has been made. This is permitted under the Sale of Goods Act or the Supply of Goods and Services Act which provide that title passes from the seller to the buyer when the parties intend it to, which can be, for example; upon delivery, upon payment or upon use. This can override the general principle that title passes on delivery and can give an unpaid supplier’s title priority over the client’s.
Such clauses need to be clearly worded, it must be established that they prevail over other documentation (such as purchase orders), and they must be drawn to the attention of the contractor and client by the supplier. If the contractor becomes insolvent, or seems likely to become insolvent, the supplier should act quickly to establish their case, giving notice of retention of title, and making clear that payment has not been made.
However, even when properly prepared, retention of tile clauses can be difficult to enforce, as generally, title passes to the client once items are incorporated into the development anyway, irrespective of whether payment has been made, and it can be difficult to establish whether payment has been made, as the client may make stage payments rather than paying in total for specific items.
Other measures a supplier might take to reduce their risk include:
- Checking the financial status of the contractor to assess the likelihood of insolvency before accepting an order.
- Arranging for items to be marked and stored separately to make clear title remains with the supplier.
- Entering into a direct contract with the client.
- Seeking advance payment.
Advance payment can be secured with an advance payment bond and the client’s title established with a vesting certificate, although vesting certificates can be similarly difficult to enforce.
NB: The term ‘Romalpa clause’ refers to the case of Aluminium Industrie Vaassen BV v Romalpa Aluminium (1976) which established the principle of extended reservation of title.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Materials on site.
- Off site goods and materials.
- Off-site goods and materials - legal issues.
- Owner.
- Parent company guarantee.
- Retention.
- Vesting certificate.
[edit] External references
- BIS, Retention of title.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.