Modelling building construction durations in Nigeria
Hassan Ahmadu, Ahmadu Bello University, Nigeria.
There is now widespread acceptance in the research community that time prediction models for construction projects should take time-influencing qualitative and managerial factors into consideration. Consequently, several multivariate models combining project scope with these factors have been developed. However, the literature also points to the limitations of these models: their application is only effective in the regions and countries where they were developed. This study aims to develop a multivariate time prediction model that is suitable for the Nigerian construction industry. A self-administered questionnaire was used to source information on the project scope factors and qualitative and managerial factors that should be considered in the study.
Principal component regression was used for the data analysis and model development, using SPSS 16.0 for windows. Three models were developed; two of them - for the public and private sector - had high R2 values. Through testing and validation they were found to be suitable for predicting construction time. By contrast, the third model, which covered all projects, had a low R2 value and was found to be an unsuitable prediction tool. The models with high R2 values serve as a useful tool to help project managers and contractors predict construction time, thereby facilitating effective planning.
This dissertation won the Merit Award, Masters Dissertation Award, CIOB International Innovation & Research Award, 2014.
The judges said, “A well-written dissertation which is tightly written and nicely argued. It draws from a broad and authoritative literature review to frame the research question in an exemplary way. It has a diligent and statistically-rigorous analysis of quantitative data gleaned from a well-designed questionnaire survey. It is an excellent piece of work and is well deserving of international recognition.”
--CIOB
Featured articles and news
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?