Modelling building construction durations in Nigeria
Hassan Ahmadu, Ahmadu Bello University, Nigeria.
There is now widespread acceptance in the research community that time prediction models for construction projects should take time-influencing qualitative and managerial factors into consideration. Consequently, several multivariate models combining project scope with these factors have been developed. However, the literature also points to the limitations of these models: their application is only effective in the regions and countries where they were developed. This study aims to develop a multivariate time prediction model that is suitable for the Nigerian construction industry. A self-administered questionnaire was used to source information on the project scope factors and qualitative and managerial factors that should be considered in the study.
Principal component regression was used for the data analysis and model development, using SPSS 16.0 for windows. Three models were developed; two of them - for the public and private sector - had high R2 values. Through testing and validation they were found to be suitable for predicting construction time. By contrast, the third model, which covered all projects, had a low R2 value and was found to be an unsuitable prediction tool. The models with high R2 values serve as a useful tool to help project managers and contractors predict construction time, thereby facilitating effective planning.
This dissertation won the Merit Award, Masters Dissertation Award, CIOB International Innovation & Research Award, 2014.
The judges said, “A well-written dissertation which is tightly written and nicely argued. It draws from a broad and authoritative literature review to frame the research question in an exemplary way. It has a diligent and statistically-rigorous analysis of quantitative data gleaned from a well-designed questionnaire survey. It is an excellent piece of work and is well deserving of international recognition.”
--CIOB
Featured articles and news
Extended reality in a post-pandemic world.
Can XR technology be leveraged in design & construction?
Or are you capping.
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.