Design and build: project brief
The project brief stage is concerned solely with preparing the project brief. the key document upon which the design will be based.
[edit] Starting the work stage and appointing additional members of the consultant team if necessary.
The client updates the business case and project execution plan to reflect comments made at the end of the previous stage. The lead consultant then co-ordinates a start-up meeting attended by the consultant team and the client to issue the revised project execution plan (and business case or part of it if appropriate), to pass on comments made at the end of the previous stage, and to agree the programme for the stage.
The consultant team or the client may identify a requirement to appoint additional consultants or specialist designers. Go to work stage: Design and build: appointment.
[edit] Preparing the project brief.
The client and consultant team discuss the required contents of the project brief and consider who the consultant team may need to consult in the preparation of the project brief. It may be appropriate to prepare a project directory of contact details and perhaps a stakeholder map.
The client informs user panels, champions and other stakeholders that will be involved in the development of the project brief that they should make time available to meet with the consultant team. The lead consultant co-ordinates the consultant team to carry out consultations with user panels, champions and other stakeholders and feeds back the outcome of consultations to the client.
The lead consultant co-ordinates the consultant team to prepare a draft project brief.
The client begins preparing, or arranges for the consultant team to begin preparing, a site waste management plan (if required). At this stage, this is a means of recording decisions made to minimise the consumption of resources and to minimise the generation of waste.
The cost consultant highlights areas of potential cost savings and areas of potential cost problems apparent in the draft project brief and prepares an elemental cost plan. The client considers advice from the cost consultant and instructs the consultant team to amend the draft project brief if necessary.
The client issues the revised project brief to the user panels, champions and other stakeholders who may propose further revisions. The client considers the proposed amendments and instructs any necessary revision of the project brief.
The cost consultant amends the elemental cost plan if necessary, and the client considers and, if satisfied, approves the project brief
If necessary the client revises the business case and project execution plan. This might include: additional value management and risk assessment exercises, re-assessment of the budget and re-assessment of the procurement route.
The project brief is issued to user panels, champions and other stakeholders who may have further involvement in the development of the project.
The client confirms that funding is available and that there is still stakeholder support for the project, and considers whether to proceed to the next stage.
[edit] Considering whether to tender the design and build contract.
At this stage the client may decide to tender the contract to design and build the development. Go to work stage: Design and build: tender.
⇒ outline plan | previous stage | next concept design by consultants or tender
Notes
- Design and build projects involve appointing a contractor to design the development and also to construct it. However, the contractor might be appointed early in the project to carry out all of the design work, or later in the project to complete a design which others have begun. This means that design tasks can be attributed either to a consultant team or the contractor depending on whether the contractor has been appointed or not. As a consequence, we include two versions of the concept design stage, detailed design stage and planning permission stage. If a two-stage tender process is adopted, then the contractor might be appointed earlier, on a pre-construction services agreement, to carry out some of the tasks attributed above to the consultant team
Featured articles and news
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.