Certificate of non completion
The date for completion of construction works (or dates for completion of sections of the works) is generally set out in the contract particulars. However, it is not uncommon for delays to cause the completion date to be missed, that is, the works are not complete, and so a certificate of practical completion cannot be issued by the date for completion.
Where the client is responsible for the delay, an extension of time may be granted, the completion date adjusted, and the contractor may be entitled to claim loss and expense.
Where the contractor is responsible for the delay, the client may be entitled to claim liquidated and ascertained damages (at a rate set out in the contract particulars).
Some contracts (such as the JCT Standard Form of Building Contract), require that the contract administrator issues the contractor with a certificate of non-completion (sometimes referred to as a ‘non-completion certificate’ or ‘non-completion notice') as a prerequisite to claiming liquidated and ascertained damages.
The certificate of non-completion gives formal written notice to the contractor that they have failed to complete the works described in the contract by the completion date that was last agreed (the original completion date may have been adjusted during the course of the works).
The contract administrator must give due consideration to any applications for extension of time before issuing a certificate of non-completion, and if there are subsequent extensions of time that result in the completion date being adjusted, and the contractor then fails to meet this adjusted date, a new certificate of non-completion must be issued.
Where the contract provides for sectional completion of the works, separate certificates of non-completion must be issued for each section that is not completed by the required date.
The client may then deduct liquidated and ascertained damages from payments otherwise due to the contractor, providing that an appropriate notice has been issued (a pay less notice) setting out the basis of the calculation. Contractors may challenge claims for liquidated and ascertained damages if the procedures and the notice periods set out in the contract have not been followed.
Some contracts (such as the JCT Minor Works Building Contract) do not require that a certificate of non-completion is issued, although it may be considered best practice to issue one anyway.
It is very important when deducting liquidated damages to ensure that the correct contractual procedures are adhered to. In the case of Octoesse LLP v Trak Special Projects Ltd. [2016], Justice Jefford held that Octoesse was not entitled to deduct liquidated damages as they had agreed to an extension of time after a certificate of non completion had been issued. The JCT Intermediate Building Contract is constructed such that:
'If the Contractor fails to complete the Works or a Section by the relevant Completion Date, the Architect/Contract administrator shall issue a certificate to that effect. If an extension of time is made after the issue of such certificate, the extension shall cancel that certificate and the Architect/Contract Administrator shall where necessary issue a further certificate.'
As Octoesse had not issued a further certificate of non completion, they were not entitled to deduct liquidated damages.
To find out more, see Octoesse LLP v Trak Special Projects Ltd.
See also: Failure to complete construction works.
[edit] Related articles on Designing Buildings
- Certificate of practical completion.
- Certificates in the construction industry.
- Completion.
- Construction contract.
- Contract administrator.
- Extension of time.
- Failure to complete construction works.
- Liquidated and ascertained damages.
- Loss and expense.
- Pay less notice.
- Practical completion.
- Octoesse LLP v Trak Special Projects Ltd
- Topping out.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
Comments
What if the completion date is not stated in the contract?