Default payment notice for construction
The Housing Grants, Construction and Regeneration Act (also known as the Construction Act) include provisions to ensure that payments are made promptly throughout the supply chain.
These provisions include:
- The right to be paid in interim, periodic or stage payments.
- The right to suspend (or part suspend) performance for non-payment and to claim costs and expenses incurred and extension of time resulting from the suspension.
- Pay when certified clauses are not allowed, and the release of retention cannot be prevented by conditions within another contract.
In addition, there are specific provisions in relation to the procedures for making payments.
- The client must issue a payment notice within five days of the date for payment, even if no amount is due. Alternatively, if the contract allows, the contractor may make an application for payment, which is treated as if it is the payment notice.
- The client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
- The notified sum is payable by the final date for payment.
- If the client (or specified person) fails to issue a payment notice, the contractor may issue a default payment notice. The final date for payment is extended by the period between when the client should have issued a payment notice and when the contractor issued the default payment notice. If the client does not issue a pay less notice, they must pay the amount in the default payment notice.
[edit] Related articles on Designing Buildings Wiki
- Cash flow.
- Construction supply chain payment charter.
- Due date.
- Extension of time.
- Fair payment practices.
- Housing Grants Construction and Regeneration Act.
- Interim certificate.
- Pay less notice.
- Payment notice.
- Remedies for late payment.
- Retention.
- Scheme for construction contracts.
- Withholding notice.
[edit] External references
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.


















Comments
If a contractor issues an application, but the payee does not issue a payment notice, then the contractor also does not issue a default notice.Would the application automatically become the default notice?