Unliquidated damages
Unliquidated damages are damages that are payable for a breach of contract, the exact amount of which has not been pre-agreed. This is in contrast with liquidated damages which are a pre-agreed when the contract is entered into.
Construction contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LADs) to the client in the event of a breach of contract - typically failing to complete the construction works by the completion date set out in the contract.
Unliquidated damages are a form of compensation which is said to be ‘at large’, that is, the amount is not predetermined with the contract is entered into, but is determined by a court (either a judge or jury) after the breach has occurred.
The advantage of unliquidated damages is that it allows for the recovery of losses that may have been impossible to foresee or to estimate with any certainty before the breach.
The disadvantage is that it leaves the client having to prove their actual losses in the event of a breach, which can be very complex, and it leaves the contractor with an unknown liability.
The client must also prove that losses flow naturally from the breach and are not 'remote'.
In standard form construction contracts, parties will sometimes insert ‘NIL’ or ‘n/a’ for the rate for liquidated damages, if they do not wish to claim liquidated damages, however, this can imply that losses for unliquidated damages are also nil. If parties wish to exclude liability for liquidated damages, they must state this clearly in the contract to avoid ambiguity, either stating that unliquidated damages apply, or deleting the clause altogether.
[edit] Related articles on Designing Buildings Wiki
- Assignment.
- Breach of contract.
- Collateral warranty.
- Completion date.
- Damages in construction contracts.
- Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd.
- Liquidated damages.
- Liquidated v unliquidated damages.
- Measure of damages.
- Practical completion.
- Remoteness.
- Substantial and other damages.
- The distinction between liquidated damages clauses and penalty clauses.
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.