The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM2: Detailed measurement for building works, a 'time-related charge' is for work, the cost of which is to be considered dependent on duration.
This is as opposed to a 'fixed charge', which is for work, the cost of which is to be considered independent of duration.
Charges may be fixed, time-related, or a combination of both.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.