Time-related charges in construction
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM2: Detailed measurement for building works, a 'time-related charge' is for work, the cost of which is to be considered dependent on duration.
This is as opposed to a 'fixed charge', which is for work, the cost of which is to be considered independent of duration.
Charges may be fixed, time-related, or a combination of both.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Conserving the Hilda Besse Building
Improving facilities, accessibility and overall appearance.
BSRIA IAQ topic guide published
Free download of TG 12/2021 available.
Electrotechincal mentors wanted
TESP works with The Youth Group to form skill sharing network.
OpenBuilt supply chain technology in development
Big tech collaborates on platform for the built environment.
Concerns raised over Future Buildings Standard
Letter signed by 21 organisations sent to MHCLG.
The infrastructure planning process
A look at the Government's strategic approach.
Steps to help reduce the spread of infection inside buildings.
Urban exploration and construction
This social media-centred hobby can be both dangerous and illegal.
Millwork wall treatment with a long and illustrious history.
Weekly workplace noise estimator tool
HSE introduces cumulative exposure calculator.
The Edwardians and their houses.
Cut off from civilian life for over 900 years.
Can net zero and levelling-up align?
Gaining green support from the carbon giants.
Receive the Designing Buildings newsletter
Click the button to subscribe.