Logic link
Logic links describe the relationships between one activity and another.
Common types of logic link include:
- Finish-to-start: One activity cannot start until a previous activity has finished.
- Lagged finish-to-start: One activity cannot start until a specific amount of time after a previous activity has finished.
- Start-to-start: One activity cannot start until another activity has started.
- Lagged start-to-start: One activity cannot start until a specific amount of time after another activity has started.
- Finish-to-finish: One activity cannot finish until another activity has finished.
- Lagged finish-to-finish: One activity cannot finish until a specific amount of time after another activity has finished.
- Lagged start and finish: One activity cannot start until a specific amount of time after another activity has started, and it cannot finish until a specific amount of time after that activity has finished.
- Negative lag: One activity can start a specific amount of time before another activity has been completed.
- Must start / must finish. The activity must start or finish on a specific date.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.