Single-stage tender
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services.
Tender procedures will vary depending on the nature of the goods or services that are being procured, but very broadly they can be classified as either single-stage or two-stage.
Single-stage tendering is the more traditional route, used when all the information necessary to calculate a realistic price is available when tendering commences:
- An invitation to tender is issued to prospective suppliers (perhaps following completion of a pre-qualification questionnaire and/or a pre-tender interview). The invitation to tender will include information describing the goods or services required in sufficient detail to enable prospective suppliers to prepare an accurate tender.
- Tenders are prepared and returned by prospective suppliers (this may involve questions and answers and a mid-tender interview to clarify the client’s requirements).
- Submitted tenders are then assessed and compared (this may involve further interviews).
- The preferred tenderer is selected and negotiations opened.
- Subject to the outcome of those negotiations the preferred tenderer may then be appointed.
See Tender for more information.
However, increasingly it is becoming useful to obtain input from prospective tenderers before there is sufficient information available for the main contract to be awarded. This can allow early input from the main contractor, or early appointment of a specialist contractor, such as a cladding contractor, before the main contract has been awarded.
A two-stage tender process may also be adopted on a design and build project where the employer's requirements are not sufficiently well developed for the contractor to be able to calculate a realistic price. In this case, the contractor will tender a fee for designing the building along with a schedule of rates that can be used to establish the construction price for the second-stage tender.
See Two-stage tender for more information.
Two-stage tendering enables the client to transfer design risk to the contractor, but the client inevitably loses leverage as the contractor becomes embedded in the team and competition is less of a threat. However, whilst tender prices for two-stage contracts may initially be higher than single-stage tenders, which are subject to full competition, the final account tends to include fewer variations and fewer claims.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.