How long it takes to get building regulations approval and how long it lasts
Contents |
[edit] Introduction
There are two types of building regulations application:
- Full plans application: Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out.
- Building notice application: On smaller projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection. However, this leaves the client at risk that completed works might not be approved, resulting in remedial costs.
[edit] Full plans application
A decision should be received within five weeks for a full plans application. However, this may be extended to two months by agreement. It is necessary then to give the building control body two working days notice before commencing the works.
It is permissible to begin works before approval has been received, however, if the works are subsequently found not to comply with the building regulations, they may have to be altered or removed.
The approval lasts for three years, within which time the building work must commence, or a fresh application will be required. This can be very important given the speed at which the regulations change, meaning that a building which has been approved, but where construction has not begun, may need to be re-designed to satisfy the new regulations.
Once the construction works have commenced, and the building control body has undertaken a commencement inspection, the approval lasts indefinitely.
A completion certificate should be received within eight weeks of completion of the building work if it complies with the regulations.
[edit] Building notice application
Works under a building notice application may begin as soon as the notice has been accepted. This is usually within two days.
The notice is valid for three years, after which it will lapse if the building work has not commenced. Once the works have commenced, the notice lasts indefinitely.
No completion certificate is issued as no plans have been submitted.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.