Payment due date in the construction industry
The Housing Grants, Construction and Regeneration Act (also known as the Construction Act) includes provisions to ensure payments are made promptly throughout the supply chain.
Section 110A(6) of the Act defines the “payment due date” as “…the date provided for by the contract as the date on which the payment is due”.
The payer must issue a payment notice within five days of the due date for payment, even if no amount is due, setting out the sum that the payer considers to be or to have been due at the payment due date, and the basis on which that sum is calculated. Alternatively, if the contract allows, the payee may make an application for payment, which is treated as if it is the payment notice. The payer must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
The contract must also provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment. The payer must pay the notified sum on or before the final date for payment.
If payment is not made on or before the final date for payment the payee can give notice under Section 112 of the Act to suspend performance of the contract.
Under the Scheme for Construction Contracts, if a construction contract fails to provide an adequate mechanism for determining when a payment becomes due, the payment shall become due, that is, payable on the later of 7 days after the assessment date or the making of a claim by the payee. The final date for payment is 17 days after the date that payment became due.
Under the Late Payment of Commercial Debts (Interest) Act 1998 the payment due date is referred to as an 'agreed payment day'.
[edit] Related articles on Designing Buildings
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.

























Comments
Thank you for the comments below. The article has been updated.
I cannot agree with the article.
The 'payment due date' and the 'final date for payment' should not be confused.
Please refer to the defiinition contained in Section 110A(6) of the Housing Grants, Construction and Regeneration Act 1996 'payment due date' means 'the date on which the payment is due' and not the date on which the payment process is invoked. The 'payment due date' is the date by which the payee should receive payment.
The 'final date for payment' is the date after which the payee can give notice under Section 112 of the Act to suspend performance of the contract because the payee has not received payment.
Under The Scheme for Construction Contracts, if a construction contract fails to provide an adequate mechanism for determining when a payment becomes due, the payment shall become due, that is, payable on the later of 7 days after the [assessment date] or the making of a claim by the payee. The 'final date for payment' is 17 days after the date that payment became due.
Moreover, under the Late Payment of Commercial Debts (Interest) Act 1998 the 'payment due date' and not the 'final date for payment' will be an 'agreed payment day' from which statutory interest will begin to run.