Construction management: outline work plan
This is an outline plan for a project following a construction management procurement route. Project plans for other procurement routes are available by clicking here.
Clicking on any of the stages will take you to the detailed tasks necessary to complete that stage. Together the tasks represent a single, consolidated project plan from the first moment it becomes apparent a project might be required right through to final evaluation of the completed project.
Construction management
Stage 1: Business justification.
Stage 2: Feasibility studies.
Stage 3: Project brief.
Stage 4: Concept design.
Stage 5: Appointing the construction manager.
Stage 6: Detailed design.
Stage 7: Production information.
Stage 8: Tender trade contracts.
Stage 9: Mobilisation.
Stage 10: Construction.
Stage 11: Occupation and defects liability period.
Stage 12: Post occupation evaluation.
Moveable stages:
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.



















Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Creating an outline work plan for construction management involves breaking down the project into manageable tasks and organizing them in a logical sequence. Here is a general outline of a work plan for construction management:
1. Project Initiation:
- Define project objectives, scope, and deliverables.
- Identify project stakeholders and establish communication channels.
- Conduct initial site assessment and feasibility studies.
- Develop project budget and timeline.
2. Pre-Construction Phase:
- Obtain necessary permits and approvals.
- Select and contract with architects, engineers, and consultants.
- Develop detailed project plans, including architectural and engineering drawings.
- Procure necessary materials, equipment, and subcontractors.
- Set up project site, including temporary facilities, safety measures, and logistics planning.
3. Construction Phase:
- Mobilize construction team and assign responsibilities.
- Coordinate with subcontractors, suppliers, and vendors.
- Monitor construction progress and ensure adherence to quality standards.
- Conduct regular site inspections and address any issues or delays.
- Manage project schedule, including tracking milestones and critical path activities.
- Implement safety protocols and monitor compliance.
- Manage project budget, including tracking expenses and cost control.
- Communicate progress to stakeholders through regular updates and meetings.
- Address any changes, variations, or unforeseen circumstances through proper change management procedures.
- Maintain documentation, including daily reports, progress photos, and records of work performed.
4. Project Completion and Closeout:
- Conduct final inspections and ensure compliance with building codes and regulations.
- Complete any necessary testing, commissioning, and certifications.
- Obtain final approvals and sign-offs from relevant authorities.
- Prepare operation and maintenance manuals, as-built drawings, and warranties.
- Coordinate project handover to the client, including training and support.
- Conduct project review and capture lessons learned.
- Finalize project accounts, including financial closeout.
- Celebrate project completion and recognize team accomplishments.
It is important to note that the specific tasks and sequence may vary depending on the size, complexity, and nature of the construction project. The work plan should be customized to align with the unique requirements of the project and the organization's standard project management processes. Regular monitoring, communication, and adjustment of the work plan are necessary throughout the construction project to ensure successful execution and delivery.