Management contract: concept design
The concept design stage is concerned with preparing a concept design for the preferred option and developing and then freezing the project brief. It may also include making an outline planning application or a detailed planning application.
In this work plan we suggest the management contractor is appointed on completion of concept design. Earlier or later appointment may result in some activities being re-allocated between the consultant team and the management contractor (for example the role of cost consultant).
[edit] Starting the work stage and appointing additional members of the consultant team if necessary.
The client updates the project execution plan to reflect comments made at the end of the previous stage. The lead consultant co-ordinates a start-up meeting attended by the consultant team and the client to receive comments made at the end of the previous stage, to issue the revised project execution plan and project brief and to agree the programme for the stage.
[edit] Preparing an initial concept design.
The consultant team carries out any additional site appraisals or surveys that may be necessary as a result of the detailed requirements of the project brief. Additional expenditure may need to be approved by the client.
The lead designer co-ordinates the preparation of an initial concept design (including outline specification) and presents these initial concept design ideas to the client. The client considers whether the initial concept design ideas represent good design quality and makes comments to the lead designer who co-ordinates incorporation of these comments into the developing concept design.
The lead designer co-ordinates consultations with user panels, champions, and other stakeholders, including statutory authorities. The lead designer then co-ordinates the incorporation of comments received into the developing concept design.
The lead designer co-ordinates a design review of the concept design and then co-ordinates any necessary amendments. The cost consultant amends the elemental cost plan and and prepares a cash flow projection for the client.
The lead consultant then co-ordinates the preparation of a concept design report which records the basic design options that merit further investigation.
The client reviews the concept design report assessing the design quality of the options presented and the extent to which it satisfies the requirements set out in the developing project brief. At this stage the client may feel it is necessary to undertake a value management exercise to ensure that optimum, whole-life solutions are being pursued.
The cost consultant amends the elemental cost plan and cash flow projection to reflect any changes to the design resulting from the value management exercise and the lead consultant co-ordinates amendments necessary to the concept design report and project brief.
The client considers the developed project brief and if satisfied, freezes the project brief and instructs the lead consultant to introduce change control procedures. The frozen project brief should be issued to user panels, champions and other stakeholders.
[edit] If necessary, making an outline planning application or detailed planning application.
The client, lead designer and architect consider whether it is appropriate to make an outline planning application or detailed planning application. If instructed by the client, the lead consultant directs the consultant team to make an outline planning application or detailed planning application. Go to work stage: Management contract: planning permission.
Featured articles and news
Homes England goes to TOWN for co-housing project
Marmalade Lane developer selected for Northstowe neighbourhood.
Cohousing and related approaches to solve housing issues
Different forms of community housing explained with examples.
Alternative and off-grid housing communities in the UK
From Hockerton Housing Project to Tinkers Bubble.
Key proposed changes in Amendment 4 to BS 7671:2018
Draft for Public Consultation from now to 3 November 2024.
World Green Building Week 9-13 September
Join in the 16th annual event led by the World GBC.
Specifying XPS in masonry cavity walls below DPC level
Moisture requirements, DPCs and third party certification.
Types of rigid foam insulation
A brief description and some of the main construction types.
Metal composite material panel systems MCM and MCP
Sandwich finishes, forms, details, core and their impacts.
Cumbria's vernacular architecture
A history of building impeded by unsettled times.
CIOB and MMC Ireland announce strategic partnership
For better working conditions, and a more productive construction sector.
More than just glass.
Grenfell Phase 2 final report for construction, at a glance
Twenty-three key issues raised and their recommendations.
Industry responds to the final Grenfell inquiry phase 2 report
Construction body responses to the long-awaited 7 volumes.
Chief construction advisers in brief
From July 2008 to November 2015.
The Grenfell phase 2 final report key summary points
And recommendations for the construction industry.
Approved Document B: Fire Safety upcoming updates
Including sprinklers in care homes, National classes and Fire resistance.
CIOB Podcast: 21st Century Construction
Catch up on the many previous episodes.
Tools and processes supporting a robust golden thread
BSRIA Handover Information and O&M Manuals guidance.
IHBC Conservation Professional Practice Principles
Spotlighted in HEF Historic Environment Overview.